Countries · India国家地区 · 印度

Where can AI data centres be built in India, and what shapes the cooling?印度哪里能建 AI 数据中心?什么在影响冷却选择?

India's IT ministry puts installed data-centre capacity at about 1,575 MW.印度电子和信息技术部称,数据中心装机容量约 1,575 MW。

It is an industry estimate. Official demand figures for 2031-32 differ, and we found no national PUE or WUE rule.这是行业估计。2031-32 年的官方需求数字不一致,也未找到全国 PUE 或 WUE 规则。

Sources checked 2026-11-06; climate from hourly observations 2020–2024.来源核查 2026-11-06;气候数据来自 2020–2024 年逐时观测。Government figure, drawn from industry estimates政府数字,来自行业估计

PUE requirement or targetPUE 要求或目标

None found未找到

No national PUE requirement in the sources read here; Uttar Pradesh raises subsidy ceilings at PUE tiers up to 1.35, 1.45 and 1.60, and Karnataka, as reported, pays Rs 20 crore once for PUE 1.00 to 1.20 (state incentives, not limits)所读来源中未找到全国 PUE 要求;北方邦按 PUE 不超过 1.35、1.45 和 1.60 分档提高补贴上限,据报道卡纳塔克邦对 PUE 1.00 至 1.20 一次性支付 2 亿卢比(邦级激励,不是限值)

State incentives only (Uttar Pradesh, Karnataka)仅有邦级激励(北方邦、卡纳塔克邦)source来源

WUE requirement or targetWUE 要求或目标

None found未找到

No national WUE requirement in the sources read here; groundwater falls under general guidelines. Karnataka, as reported, reimburses water charges for WUE 0.7 to 1.3 L/kWh, and Uttar Pradesh tells operators to adopt closed-loop systems and treated wastewater, with no WUE figure所读来源中未找到全国 WUE 要求;地下水适用一般性指南。据报道卡纳塔克邦对 WUE 为 0.7 至 1.3 L/kWh 的数据中心项目报销水费,北方邦要求运营商采用闭式系统和再生水,但没有 WUE 数值

None found nationally in the sources read here所读来源中未找到全国要求State incentive in Karnataka, as reported卡纳塔克邦有邦级激励(据报道)source来源

Power build-out电力建设规模

1,575MW

Installed data-centre capacity given to Parliament by MeitY in August 2026, drawn from industry estimates; load basis not stated. Official demand figures for 2031-32 differ: 13.56 GW, about 17 GW, and an additional 26.3 GW from AI data centresMeitY 2026 年 8 月向议会提供的数据中心装机容量,来自行业估计,未说明负荷口径。2031-32 年的官方需求数字不一致:13.56 GW、约 17 GW,以及 AI 数据中心新增 26.3 GW

Government figure, drawn from industry estimates政府数字,来自行业估计source来源

Biggest constraint最大约束

Power电力

The biggest constraint is getting power to the site: industry consultations by the think tank CEEW put power first and name grid connectivity approvals among the delays, and a consultancy says commitments are nearing Navi Mumbai's allocation of about 6 GW. The government says national transmission is adequately prepared and that data centres are under 1% of installed power capacity.最大约束是把电送到场地:智库 CEEW 的行业访谈把电力排在首位,并把并网审批列为延误原因之一;一家咨询机构称,已承诺容量正接近新孟买约 6 GW 的分配容量。政府则称全国输电系统已做好充分准备,数据中心不到电力装机容量的 1%。

Our reading of the sourced rules本站对有来源规则的解读Second: water其次:水source来源
Data-centre power in India: installed capacity to 2026, and official demand estimates for 2031-32 (MW)印度数据中心电力:至 2026 年的装机容量,以及 2031-32 年的官方需求估计(MW)
Installed capacity: 2020装机容量:2020 年 375 MW375 MWInstalled capacity: 2025装机容量:2025 年 ~1,500 MW约 1,500 MWInstalled capacity: August 2026装机容量:2026 年 8 月 ~1,575 MW约 1,575 MWDemand estimate for 2031-32, stated March 20262031-32 年需求估计,2026 年 3 月给出 13,560 MW (forecast)13,560 MW(预测)Demand estimate up to 2031-32 (CEA), stated August 2026至 2031-32 年需求估计(CEA),2026 年 8 月给出 ~17,000 MW (forecast)约 17,000 MW(预测)
Installed, 20202020 装机 375 MWInstalled, 20252025 装机 ~1,500 MWInstalled, 20262026 装机 ~1,575 MWDemand, Mar 2026需求,3 月给出 13,560 MWDemand, Aug 2026需求,8 月给出 ~17,000 MW

Solid: installed capacity given to Parliament by the IT ministry; it says these are industry estimates and does not state the load basis. Hollow: estimates of demand in 2031-32. Capacity and demand are different quantities and are not added.实心:电子和信息技术部向议会提供的装机容量;该部称这些数字是行业估计,未说明负荷口径。空心:2031-32 年的需求估计。容量和需求是不同的量,不相加。

Data-centre power in India: installed capacity to 2026, and official demand estimates for 2031-32 (MW)印度数据中心电力:至 2026 年的装机容量,以及 2031-32 年的官方需求估计(MW)

Table表格

Measure指标MWKind类型Source来源
Installed capacity: 2020装机容量:2020 年375actual实际link链接
Installed capacity: 2025装机容量:2025 年around 1,500约 1,500actual实际link链接
Installed capacity: August 2026装机容量:2026 年 8 月about 1,575约 1,575actual实际link链接
Demand estimate for 2031-32, stated March 20262031-32 年需求估计,2026 年 3 月给出13,560forecast预测link链接
Demand estimate up to 2031-32 (CEA), stated August 2026至 2031-32 年需求估计(CEA),2026 年 8 月给出about 17,000约 17,000forecast预测link链接

Sources来源

  1. MeitY reply to the Rajya Sabha, 7 August 2026 (Press Information Bureau)MeitY 对联邦院的答复,2026 年 8 月 7 日(新闻信息局) 2026-08-12
  2. MeitY reply to the Rajya Sabha, 13 March 2026 (Press Information Bureau)MeitY 对联邦院的答复,2026 年 3 月 13 日(新闻信息局) 2026-03-13
  3. MeitY reply to the Rajya Sabha, 7 August 2026 (Press Information Bureau)MeitY 对联邦院的答复,2026 年 8 月 7 日(新闻信息局) 2026-08-12
  4. MeitY reply to the Rajya Sabha, 13 March 2026 (Press Information Bureau)MeitY 对联邦院的答复,2026 年 3 月 13 日(新闻信息局) 2026-03-13
  5. MeitY reply to the Rajya Sabha, 7 August 2026 (Press Information Bureau)MeitY 对联邦院的答复,2026 年 8 月 7 日(新闻信息局) 2026-08-12

Method and notes方法和说明

The first three points are installed capacity as the electronics and IT ministry (MeitY) gave it to Parliament; the replies do not say whether this is IT or total load, and MeitY told a parliamentary committee that these figures are industry estimates. The last two points are estimates of data-centre power demand up to 2031-32, as stated in March and August 2026; they do not say whether this is peak or average. Capacity and demand are different quantities and are not added. On 27 July 2026 the Power Ministry separately gave an additional load of 26.3 GW from AI data centres by 2031-32; that figure has a different scope and is not shown here.前三个点是电子和信息技术部(MeitY)向议会提供的装机容量;答复未说明是 IT 负荷还是总负荷,MeitY 曾向议会委员会表示这些数字来自行业估计。后两个点是 2026 年 3 月和 8 月给出的至 2031-32 年数据中心电力需求估计;未说明是峰值还是平均。容量和需求是不同的量,不相加。2026 年 7 月 27 日,电力部另外给出至 2031-32 年 AI 数据中心新增负荷 26.3 GW;该数字范围不同,未在此显示。

Thermal meaning热管理含义

With no national PUE or WUE rule found, the cooling plant is set by the operator, state incentives and the power the site can draw. At a 10 K approach a dry cooler alone makes W32 water in about 4% of hours in Mumbai and 1% in Chennai but 43% in Bengaluru, about 900 m up; at W41 the shares are about 83%, 77% and 96%, so the coastal hubs keep chillers for the hot hours.未找到全国 PUE 或 WUE 规则,冷站设计取决于运营商、邦级激励和场地能取到多少电。接近温差 10 K 时,干冷器单独供出 W32 水的时间,孟买约占全年 4%,金奈约 1%,海拔约 900 米的班加罗尔约 43%;W41 水分别约 83%、77% 和 96%,所以沿海枢纽在炎热时段仍需要冷水机组。

Our engineering reading of the rules and climate. 本站对规则和气候的工程判断。Hours for Mumbai (Chhatrapati Shivaji Airport), Chennai (Chennai Airport), Bengaluru (Kempegowda Airport), Hyderabad (Rajiv Gandhi Airport), Visakhapatnam (Visakhapatnam Airport) and Delhi (Indira Gandhi Airport) on the Countries page国家地区页中孟买(贾特拉帕蒂·希瓦吉机场)、金奈(金奈机场)、班加罗尔(肯佩戈达机场)、海得拉巴(拉吉夫·甘地机场)、维沙卡帕特南(维沙卡帕特南机场)和德里(英迪拉·甘地机场)的小时数

Go deeper继续深入

Policies政策10 sourced facts10 条有来源事实
  • MeitY's Data Centre Policy 2020 is marked as a draft for discussion. It proposes Data Centre Economic Zones, essential-service status and open access, and encourages renewable energy; the copy read sets no PUE or WUE figure.MeitY 的《2020 数据中心政策》标注为讨论稿。它提出设立数据中心经济区、赋予基本服务地位并实行开放接入,并鼓励可再生能源;所读副本未设定 PUE 或 WUE 数值。 draft草案 2020-11 source来源
  • Data centres with at least 5 MW of IT load are on the Finance Ministry's Harmonized Master List of Infrastructure sub-sectors.IT 负荷不低于 5 MW 的数据中心列入财政部《基础设施子行业统一总清单》。 in force生效中 2022-10-11 source来源
  • The Union Budget 2026-27 proposed a tax holiday until 2047 for a foreign company selling cloud services to customers globally using data-centre services from India; Indian customers must be served through an Indian reseller. The Budget memorandum limits it to data centres set up under an approved scheme, notified by MeitY, and owned and operated by an Indian company, and a 15% safe harbour on cost applies to a related Indian company. These texts contain no PUE or water condition.2026-27 联邦预算提议,外国公司利用印度的数据中心服务向全球客户销售云服务,可享受至 2047 年的免税期;服务印度客户须通过印度经销商。预算备忘录把范围限于按批准方案设立、经 MeitY 公告、由印度公司拥有和运营的数据中心;关联印度公司适用成本加 15% 的安全港。这些文本没有 PUE 或用水条件。 in force from 2026-04-01自 2026-04-01 生效 2026-02-01 source来源
  • NITI Aayog's Data Centre Evaluation Framework is guidance for states, not regulation. It asks for a power plan validated jointly by developer, distribution company and state transmission utility; demand-response readiness above 20 MW; design and guaranteed PUE; standardised PUE, WUE and CUE measurement; and desalinated water where basin stress rules out more fresh water.NITI Aayog 的《数据中心评估框架》是给各邦的指引,不是法规。它要求开发商、配电公司和邦输电公司共同验证供电计划;20 MW 以上具备需求响应能力;提供设计和保证 PUE;统一 PUE、WUE 和 CUE 的计量;流域压力不允许再取淡水时使用淡化水。 advice建议 2026-10-14 source来源
  • Gujarat notified its Data Centre Policy 2026-29, planning 7.5 GW of capacity; eligible projects must source at least 51% of operational electricity from renewable and green sources. No PUE or WUE figure appears in the reports read.古吉拉特邦正式发布了《2026-29 数据中心政策》,计划 7.5 GW 容量;符合条件的项目,其运营用电须至少有 51% 来自可再生和绿色能源。所读报道中没有 PUE 或 WUE 数值。 in force (policy)生效(政策) 2026-08-07 source来源
  • Maharashtra widened its Integrated Green Data Centre Parks policy from three parks to twenty, statewide, and cut the required green-energy share for core activities from 100% to 51%, by a Government Resolution of 9 June 2026, according to a trade report.据行业报道,马哈拉施特拉邦以 2026 年 6 月 9 日的政府决议,把综合绿色数据中心园区政策从三个园区扩大到全邦二十个,并把核心活动的绿色能源比例要求从 100% 降至 51%。 in force (policy)生效(政策) 2026-06-09 source来源
  • Andhra Pradesh's IT minister says at least 70% of the energy used by data centres must be renewable, and that water for the Visakhapatnam cluster is to come through the Polavaram project, with incentives for desalination.安得拉邦 IT 部长称,数据中心至少 70% 的能源须来自可再生能源;维沙卡帕特南集群的用水将经 Polavaram 工程供应,并对海水淡化提供激励。 announced已宣布 2026-09-25 source来源
  • India's Digital Personal Data Protection Rules 2025 let the central government require Significant Data Fiduciaries to keep specified personal data in India. Other personal data may leave India, subject to requirements the government may set on making it available to a foreign state. No general localisation duty was found in these rules.印度《2025 数字个人数据保护规则》允许中央政府要求重要数据受托人把指定的个人数据留在印度境内。其他个人数据可以出境,但政府可就向外国提供这些数据设定要求。这些规则中未发现一般性本地化义务。 in force from 2027-05自 2027-05 生效 2025-11-13 source来源
  • The National Green Tribunal flagged gaps in the clearance of a 512 MW data centre at Visakhapatnam, granted as a building project. It said public consultation and site-specific conditions were not taken into account, that heat generation appeared to be overlooked, that the environmental rules have no category for mega data centres, and that the 2020 draft policy was never finalised, according to LiveLaw.据 LiveLaw 报道,国家绿色法庭指出,维沙卡帕特南一个 512 MW 数据中心的环境许可存在缺口:它按建筑项目审批,未考虑公众咨询和场地特定条件,发热问题似被忽略;环境规定中没有超大型数据中心的类别,2020 年政策草案也未最终确定。 actual实际 2026-10-30 source来源
  • The Green Energy Open Access Rules of 2022 let any consumer with a load of 100 kW or more, down from 1 MW, buy renewable power directly through the grid.2022 年《绿色能源开放接入规则》允许负荷 100 kW 及以上(此前为 1 MW)的任何用户通过电网直接购买可再生电力。 in force生效中 2022-06-06 source来源
Efficiency rules能效要求3 sourced facts3 条有来源事实
  • Uttar Pradesh's Data Centre Policy 2026 sets no PUE limit. It raises subsidy ceilings in three PUE tiers (up to 1.35, 1.35 to 1.45, 1.45 to 1.60) for parks and units with a top-two green data-centre certification. At PUE up to 1.35, a park's overall interest-subsidy ceiling rises by ₹4 crore and its annual ceiling by ₹0.8 crore.北方邦《2026 数据中心政策》未设定 PUE 限值。对获得前两级绿色数据中心认证的园区和单体项目,按三档 PUE(不超过 1.35、1.35 至 1.45、1.45 至 1.60)提高补贴上限。PUE 不超过 1.35 时,园区的利息补贴总上限提高 4,000 万卢比(₹4 crore),年度上限提高 800 万卢比(₹0.8 crore)。 condition of state incentives邦级激励条件 2026-07 source来源
  • Karnataka's Sustainable Data Centre Policy 2026-31, as reported, targets 1 GW of IT load by 2031, requires plant-wise reporting of PUE and WUE, and pays Rs 20 crore once to units reaching PUE 1.00 to 1.20, after they hold it for three consecutive years.据报道,卡纳塔克邦《2026-31 可持续数据中心政策》目标是到 2031 年达到 1 GW IT 负荷,要求按站点报告 PUE 和 WUE,并向 PUE 达到 1.00 至 1.20 且连续保持三年的数据中心项目一次性支付 2 亿卢比(Rs 20 crore)。 condition of state incentives邦级激励条件 2026-09-30 source来源
  • MeitY told Parliament that the Bureau of Indian Standards has published standards on PUE, CUE, CER and WUE, and that the Bureau of Energy Efficiency's building codes (ECBC 2017, ECSBC 2024) include provisions relevant to data centres. The reply sets no PUE or WUE limit and does not say whether the standards are mandatory.MeitY 向议会表示,印度标准局已发布 PUE、CUE、CER 和 WUE 标准,能效局的建筑规范(ECBC 2017、ECSBC 2024)含有与数据中心相关的条款。答复未设定 PUE 或 WUE 限值,也未说明这些标准是否强制。 published standard已发布标准 2026-08-07 source来源
Power电力5 sourced facts5 条有来源事实
  • The think tank CEEW reports from its industry consultations that power is the first hurdle and land acquisition the next, and that perceived water risk is low, though this may understate future constraints. Stakeholders name grid connectivity approvals, building plan sanctions and fire clearances as causes of delay.智库 CEEW 根据行业访谈称,电力是首要障碍,其次是土地获取;受访方认为用水风险较低,但这可能低估未来的约束。相关方指出并网审批、建筑规划许可和消防许可是造成延误的原因。 statement (think tank)声明(智库) 2026-02 source来源
  • The consultancy Structure Research says MSEDCL, the Maharashtra distribution utility, has allocated about 6 GW of grid capacity to data centres in Navi Mumbai, and that committed and under-construction capacity is approaching that limit, moving new builds to outer zones such as Panvel, Taloja and Rasayani.咨询机构 Structure Research 称,马哈拉施特拉邦配电公司 MSEDCL 已向新孟买的数据中心分配约 6 GW 电网容量,已承诺和在建容量正接近这一上限,新项目因此转向 Panvel、Taloja 和 Rasayani 等外围地区。 statement (consultancy)声明(咨询机构) 2026 source来源
  • The government's position differs: MeitY told Parliament that the national transmission system is adequately prepared to supply power reliably across regions.政府的立场不同:MeitY 向议会表示,全国输电系统已做好充分准备,可在各地区可靠供电。 statement (government)声明(政府) 2026-03-13 source来源
  • The CEA has set up a committee on how large data centres affect the power system and grid stability, after Odisha raised concerns about large collective power purchases by operators, according to a KNN report that cites the Economic Times.据 KNN 援引《经济时报》报道,在奥里萨邦就运营商大规模集体购电表达担忧后,CEA 成立了委员会,研究大型数据中心对电力系统和电网稳定的影响。 actual实际 2026-10-01 source来源
  • A market report says the 26.3 GW covers 11 states, that developers have applied for grid connectivity for about 17 GW of it, and that applications for the remaining 9.3 GW are still pending. If correct, this could link the 17 GW and 26.3 GW figures, but no ministry document stating it was found.一份市场报道称,26.3 GW 覆盖 11 个邦,开发商已就其中约 17 GW 申请并网,其余 9.3 GW 的申请仍未完成。如果属实,这可能解释 17 GW 与 26.3 GW 的关系,但未找到说明这一点的部委文件。 actual实际 2026-08-27 source来源
Water水6 sourced facts6 条有来源事实
  • The water ministry (Jal Shakti) told Parliament that MeitY has received no concerns about data-centre water use, and that groundwater extraction is controlled by general guidelines (S.O. 3289(E) of 24 September 2020, amended 29 March 2023). The reply gives no water limit or WUE requirement for data centres.水利部(Jal Shakti)向议会表示,MeitY 未收到有关数据中心用水的关切;地下水开采由一般性指南管理(2020 年 9 月 24 日 S.O. 3289(E),2023 年 3 月 29 日修订)。答复未给出针对数据中心的用水限值或 WUE 要求。 in force生效中 2026-03-30 source来源
  • Newslaundry reports that the Central Ground Water Board found Bengaluru extracts almost 10 times what it recharges each year, and that Devanahalli, which hosts several data centres, uses 169% of permissible extraction. It also reports Karnataka's IT minister telling the Assembly that each MW needs 25 million litres of water a year.据 Newslaundry 报道,中央地下水委员会发现班加罗尔每年的地下水开采量几乎是补给量的 10 倍;有多个数据中心的 Devanahalli 开采量达到允许开采量的 169%。报道还称,卡纳塔克邦 IT 部长在邦议会表示,每 MW 每年需要 2,500 万升水。 actual实际 2026-04-16 source来源
  • Down To Earth reports that Chennai nearly ran out of water in 2019 and brought in supplies by train, and that the city still relies heavily on erratic rains, desalination plants and groundwater.据 Down To Earth 报道,金奈 2019 年几乎断水,曾用火车运水;该市至今仍严重依赖不稳定的降雨、海水淡化厂和地下水。 actual实际 2026-07-04 source来源
  • The Andhra Pradesh High Court refused to stay construction of the Google-Adani data centre at Visakhapatnam, while questioning its environmental clearance and its proposed water and electricity use, according to a legal news report.据法律新闻报道,安得拉邦高等法院拒绝叫停维沙卡帕特南的 Google-Adani 数据中心施工,同时质询其环境许可以及拟议的用水和用电。 actual实际 2026-08-24 source来源
  • Karnataka's Sustainable Data Centre Policy 2026-31, as reported, reimburses 100% of water charges, up to Rs 30 lakh a year for two years, for data-centre units at a WUE of 0.7 to 1.3 litres per kWh held for at least three years. A separate measure reimburses treated-water charges, up to Rs 8 lakh a year for five years.据报道,卡纳塔克邦《2026-31 可持续数据中心政策》对 WUE 为 0.7 至 1.3 L/kWh 且保持至少三年的数据中心项目,报销 100% 水费,每年最高 300 万卢比(Rs 30 lakh),为期两年。另一项措施报销再生水费用,每年最高 80 万卢比(Rs 8 lakh),为期五年。 condition of state incentives邦级激励条件 2026-09-30 source来源
  • Uttar Pradesh's Data Centre Policy 2026 says operators shall adopt water-efficient cooling, closed-loop systems and treated-wastewater reuse, and that water availability is assessed before land is allocated in state-agency areas. It sets no WUE figure.北方邦《2026 数据中心政策》规定,运营商须采用节水冷却、闭式系统和再生水回用;在邦属机构辖区,分配土地前须评估水源条件。政策未设定 WUE 数值。 in force (policy)生效(政策) 2026-07 source来源
Projects项目10
Company公司Place地点As stated by the company公司表述Kind类型Source来源
Google with AdaniConneX and AirtelVisakhapatnam, Andhra Pradesh安得拉邦维沙卡帕特南US$15 billion investment (company figure, 2026-2030); a campus capable of gigawatt-scale compute投资 150 亿美元(公司数字,2026-2030 年);可达吉瓦级算力的园区investment投资link链接
Vizag Hyperscale Data Centre Park (Adani Infra)Adavivaram and Mudasarlova, Visakhapatnam维沙卡帕特南 Adavivaram 和 Mudasarlova512 MW proposed; environmental clearance of 10 June 2026 under challenge at the National Green Tribunal拟建 512 MW;2026 年 6 月 10 日的环境许可正在国家绿色法庭受到质疑capacity容量link链接
Reliance IndustriesJamnagar, Gujarat古吉拉特邦贾姆纳加尔first 120 MW of AI compute due by the end of 2026, as reported from the annual meeting首批 120 MW AI 算力计划于 2026 年底投运,据年度股东大会报道capacity容量link链接
TCS HyperVault with OpenAIIndia; site not stated in the report read印度;所读报道未说明地点100 MW of AI-ready capacity, with an option to scale to 1 GW, as reported100 MW AI 就绪容量,可选择扩展至 1 GW,据报道capacity容量link链接
MicrosoftIndia; includes the India South Central region in Hyderabad印度;包括海得拉巴的 India South Central 区域US$17.5 billion over CY2026-2029, covering infrastructure, skilling and operations, not capacity2026-2029 年 175 亿美元,涵盖基础设施、技能培训和运营,不是容量investment投资link链接
AmazonIndia; AWS regions in Mumbai and Hyderabad印度;AWS 区域位于孟买和海得拉巴more than US$35 billion through 2030 across all Amazon businesses, so not a data-centre figure至 2030 年超过 350 亿美元,覆盖亚马逊全部业务,因此不是数据中心数字investment投资link链接
Sify Infinit SpacesNavi Mumbai and Chennai新孟买和金奈103 MW across two data centres, financed with the International Finance Corporation两个数据中心共 103 MW,由国际金融公司提供融资capacity容量link链接
YottaGreater Noida, Uttar Pradesh北方邦大诺伊达campus at 60 MW today, able to expand to 250 MW, as reported; more than US$2 billion for an NVIDIA AI hub园区目前 60 MW,可扩展至 250 MW,据报道;超过 20 亿美元用于 NVIDIA AI 中心
liquid cooling, as reported液冷,据报道
capacity容量link链接
Yotta (in Hiranandani Fortune City)Panvel, Navi Mumbai新孟买 PanvelNM1: 52 MW of IT power, with more buildings possible on the campusNM1:52 MW IT 负荷,园区还可增加建筑
design PUE 1.4 (company figure)设计 PUE 1.4(公司数字)
capacity容量link链接
Lodha DevelopersPalava/Ambernath, Thane district, as reported塔那县 Palava/Ambernath(据报道)Rs 30,000 crore memorandum with Maharashtra for a green data-centre park; an agreement, not capacity与马哈拉施特拉邦签署 3,000 亿卢比(Rs 30,000 crore)绿色数据中心园区备忘录;是协议,不是容量investment投资link链接

Capacity and investment are different measures and are never added. Capacities are the companies' own figures, with their qualifiers.容量和投资是不同的量,不相加。容量为公司自己的数字,保留其限定词。

What is not covered未覆盖的内容

No national PUE or WUE requirement, no notified national data-centre policy, no data-centre tariff class, no published grid-connection queue and no moratorium were found in the sources read here. State measures found on PUE and WUE are incentives. Official demand figures for 2031-32 differ (13.56 GW, about 17 GW, and an additional 26.3 GW from AI data centres), and how they relate is not stated. MeitY says it keeps no official capacity data, and consultancies give different mid-2026 figures. Not read: the CEA's own data-centre estimate, the Karnataka and Maharashtra 2026 texts, the Gujarat policy PDF and Tamil Nadu's 2021 policy, whose period reportedly ended on 31 March 2026. No water-stress data specific to Mumbai data centres and no measured national WUE or PUE were found. Project cooling is rarely stated. No usable public source was read for CtrlS. Climate data come from NOAA hourly observations.所读来源中未找到全国 PUE 或 WUE 要求、正式发布的全国数据中心政策、数据中心专用电价类别、公开的并网排队信息或暂停令。找到的邦级 PUE 和 WUE 措施都是激励。2031-32 年的官方需求数字不一致(13.56 GW、约 17 GW,以及 AI 数据中心新增 26.3 GW),它们的关系未说明。MeitY 称未保存官方容量数据,各咨询机构给出的 2026 年年中数字也不同。未读:CEA 自身的数据中心估计、卡纳塔克邦和马哈拉施特拉邦 2026 年政策原文、古吉拉特邦政策 PDF,以及据称已于 2026 年 3 月 31 日到期的泰米尔纳德邦 2021 年政策。未找到针对孟买数据中心的水压力数据,也未找到全国实测 WUE 或 PUE。项目很少说明冷却方式。未读到 CtrlS 的可用公开来源。气候数据来自 NOAA 逐时观测。

Database view: every India number and fact on this page, with its source wording数据库视图:本页全部印度数字和事实及来源原文172 rows172 行
Showing显示 172Quotes are the source's own wording. Main series: The first three points are installed capacity as the electronics and IT ministry (MeitY) gave it to Parliament; the replies do not say whether this is IT or total load, and MeitY told a parliamentary committee that these figures are industry estimates. The last two points are estimates of data-centre power demand up to 2031-32, as stated in March and August 2026; they do not say whether this is peak or average. Capacity and demand are different quantities and are not added. On 27 July 2026 the Power Ministry separately gave an additional load of 26.3 GW from AI data centres by 2031-32; that figure has a different scope and is not shown here. Climate rows: hours a year (2020–2024 average) a dry cooler alone can make the water, from NOAA hourly observations, assuming the dry cooler supplies the facility water directly (a plate heat exchanger in between adds its own approach, so fewer hours). Missing hours are scaled from the observed share of each year to 8,760 hours.引文为来源原文。主序列:前三个点是电子和信息技术部(MeitY)向议会提供的装机容量;答复未说明是 IT 负荷还是总负荷,MeitY 曾向议会委员会表示这些数字来自行业估计。后两个点是 2026 年 3 月和 8 月给出的至 2031-32 年数据中心电力需求估计;未说明是峰值还是平均。容量和需求是不同的量,不相加。2026 年 7 月 27 日,电力部另外给出至 2031-32 年 AI 数据中心新增负荷 26.3 GW;该数字范围不同,未在此显示。气候行:仅靠干冷器即可制水的年小时数(2020–2024 年平均),来自 NOAA 逐时观测,假设干冷器直接供设施水(中间若有板式换热器,会再增加其接近温差,小时数更少)。缺测小时按每年已观测的比例折算为 8,760 小时。
Field字段Fact事实Status状态Date日期Source wording来源原文Source来源
Build scale建设规模Data-centre power in India: installed capacity to 2026, and official demand estimates for 2031-32 (MW)印度数据中心电力:至 2026 年的装机容量,以及 2031-32 年的官方需求估计(MW): Installed capacity: 2020装机容量:2020 年, 375 MWactual实际2026-08-12The installed capacity has grown from 375 MW in 2020 to current capacity of about 1575 MW.link链接
Build scale建设规模Data-centre power in India: installed capacity to 2026, and official demand estimates for 2031-32 (MW)印度数据中心电力:至 2026 年的装机容量,以及 2031-32 年的官方需求估计(MW): Installed capacity: 2025装机容量:2025 年, around 1500约 1500 MWactual实际2026-03-13The total data centre capacity in the country has increased from about 375 MW in 2020 to around 1500 MW by 2025.link链接
Build scale建设规模Data-centre power in India: installed capacity to 2026, and official demand estimates for 2031-32 (MW)印度数据中心电力:至 2026 年的装机容量,以及 2031-32 年的官方需求估计(MW): Installed capacity: August 2026装机容量:2026 年 8 月, about 1575约 1575 MWactual实际2026-08-12The installed capacity has grown from 375 MW in 2020 to current capacity of about 1575 MW.link链接
Build scale建设规模Data-centre power in India: installed capacity to 2026, and official demand estimates for 2031-32 (MW)印度数据中心电力:至 2026 年的装机容量,以及 2031-32 年的官方需求估计(MW): Demand estimate for 2031-32, stated March 20262031-32 年需求估计,2026 年 3 月给出, 13,560 MWforecast预测2026-03-13As per information available with the Ministry of Power, electricity demand from data centres is estimated to reach 13.56 GW by 2031–32.link链接
Build scale建设规模Data-centre power in India: installed capacity to 2026, and official demand estimates for 2031-32 (MW)印度数据中心电力:至 2026 年的装机容量,以及 2031-32 年的官方需求估计(MW): Demand estimate up to 2031-32 (CEA), stated August 2026至 2031-32 年需求估计(CEA),2026 年 8 月给出, about 17000约 17000 MWforecast预测2026-08-12As per Central Electricity Authority (CEA), Ministry of Power (MoP), the power demand of data centres is estimated to be about 17 GW up to 2031-32.link链接
Build scale建设规模The electronics and IT ministry (MeitY) told Parliament that installed data-centre capacity grew from 375 MW in 2020 to about 1,575 MW now, and that this is less than 1% of India's installed power capacity.电子和信息技术部(MeitY)向议会表示,数据中心装机容量从 2020 年的 375 MW 增至目前约 1,575 MW,不到全国电力装机容量的 1%。actual实际2026-08-07The installed capacity has grown from 375 MW in 2020 to current capacity of about 1575 MW. … The current data centres capacity across the country is less than 1% of the current installed power capacity.link链接
Build scale建设规模A parliamentary committee report records MeitY saying that it keeps no official data on data-centre capacity and that the figures it gives are industry estimates. The same report also uses another estimate of 520 MW for 2020.议会委员会报告记载,MeitY 称其未保存数据中心容量的官方数据,所给数字来自行业估计。同一报告还使用了 2020 年 520 MW 的另一估计。actual实际2026-09-25Officially no data is maintained in MeitY regarding capacity of Data Centres. However as per industry estimates, Data centre capacity in the country has grown from 375 MW in 2020 to more than 1500 MW till 2025. Committee on External Affairs, Seventeenth Report, para 5.16, read from a copy hosted by MediaNama; the copy on the Parliament website was not read.外交事务委员会第十七次报告第 5.16 段,读自 MediaNama 托管的副本;未读议会网站上的副本。link链接
Build scale建设规模ThePrint reports that the MeitY Secretary told a parliamentary committee that data centres are using approximately 1,020 MW, that this may exceed 2,000 MW in two years, and that 4 to 5 GW may be needed in four to five years.据 ThePrint 报道,MeitY 秘书向议会委员会表示,数据中心目前使用约 1,020 MW,两年内可能超过 2,000 MW,四到五年内可能需要 4 至 5 GW。actual实际2026-03-31“Currently, data centres are using approximately 1,020 megawatts,” the Secretary told the committee. “In two years that will double. It may go above 2,000 megawatts. It is possible that in four to five years, four to five gigawatts of power will be needed. Planning for this is happening now.”link链接
Build scale建设规模MeitY, citing the Central Electricity Authority (CEA), told Parliament that data-centre power demand is estimated at about 17 GW up to 2031-32.MeitY 援引中央电力局(CEA)向议会表示,至 2031-32 年数据中心电力需求估计约 17 GW。forecast预测2026-08-07As per Central Electricity Authority (CEA), Ministry of Power (MoP), the power demand of data centres is estimated to be about 17 GW up to 2031-32.link链接
Build scale建设规模On 27 July 2026 the Minister of State for Power told Parliament that an additional load of 26.3 GW from AI data centres is projected by 2031-32, mainly served by renewable capacity. The replies read here do not explain how this relates to the 13.56 GW given in March or the 17 GW given in August.2026 年 7 月 27 日,电力部国务部长向议会表示,预计至 2031-32 年 AI 数据中心新增负荷 26.3 GW,主要由可再生能源装机供电。所读答复未说明它与 3 月的 13.56 GW 和 8 月的 17 GW 是什么关系。forecast预测2026-07-27an additional load of 26.3 GW from Artificial Intelligence (AI) Data Centres is projected by 2031–32, which is expected to be integrated into the grid and primarily served by renewable energy capacity.link链接
Build scale建设规模In February 2025 the Power Ministry, citing an industry report, gave 854 MW of IT load and 5,640 MW of power demand from upcoming data centres by FY2031-32 (3,535 MW by FY2027-28). Its annexure lists 2,970 MW in Chennai, 1,500 MW at Shadnagar in Telangana and 700 MW in Mumbai; transmission is planned for Navi Mumbai and Shadnagar.2025 年 2 月,电力部援引一份行业报告,给出 854 MW IT 负荷,以及至 2031-32 财年新建数据中心 5,640 MW 的电力需求(至 2027-28 财年 3,535 MW)。其附件列出金奈 2,970 MW、特伦甘纳邦 Shadnagar 1,500 MW、孟买 700 MW;已为新孟买和 Shadnagar 规划输电系统。forecast预测2025-02-10As per an Industry Research Report, the Data Centre Capacity in India is 854 MW of Information Technology (IT) load. Power Demand due to upcoming data centers in India is likely to arise and estimated to be 5,640 MW by FY 2031-32. … Transmission system has been planned for upcoming data centers at Navi Mumbai, Maharashtra, and Shadnagar, Telangana.link链接
Build scale建设规模The consultancy Savills India estimates operational stock at 1.8 GW IT after 258 MW IT was added in the first half of 2026, expects more than 7 GW IT by 2030, and says adequate power and suitable land remain a major challenge.咨询机构 Savills India 估计,2026 年上半年新增 258 MW IT 负荷后,在运存量为 1.8 GW IT,预计 2030 年超过 7 GW IT,并称充足的电力和合适的土地仍是主要挑战。statement (consultancy)声明(咨询机构)2026-07-22The expansion increased the country's total operational data centre stock to 1.8 GW IT. The consultancy expects India's data centre capacity to exceed 7 GW IT by 2030, supported by strong demand from hyperscalers and large enterprises. However, the availability of adequate power supply and suitable land continues to remain a major challenge for future data centre development across key markets.link链接
Power电力The think tank CEEW reports from its industry consultations that power is the first hurdle and land acquisition the next, and that perceived water risk is low, though this may understate future constraints. Stakeholders name grid connectivity approvals, building plan sanctions and fire clearances as causes of delay.智库 CEEW 根据行业访谈称,电力是首要障碍,其次是土地获取;受访方认为用水风险较低,但这可能低估未来的约束。相关方指出并网审批、建筑规划许可和消防许可是造成延误的原因。statement (think tank)声明(智库)2026-02Our consultations further suggest that, after power, land acquisition is the most significant hurdle at present, while the perceived water-availability risk remains low. However, this likely reflects the sector's early stage and may understate future constraints as deployments scale up.link链接
Power电力The consultancy Structure Research says MSEDCL, the Maharashtra distribution utility, has allocated about 6 GW of grid capacity to data centres in Navi Mumbai, and that committed and under-construction capacity is approaching that limit, moving new builds to outer zones such as Panvel, Taloja and Rasayani.咨询机构 Structure Research 称,马哈拉施特拉邦配电公司 MSEDCL 已向新孟买的数据中心分配约 6 GW 电网容量,已承诺和在建容量正接近这一上限,新项目因此转向 Panvel、Taloja 和 Rasayani 等外围地区。statement (consultancy)声明(咨询机构)2026MSEDCL has allocated approximately 6 GW of grid power capacity to data centres in the key cluster of Navi Mumbai. … capacity already approaching that threshold on a net MW basis, further large-scale grid-dependent expansion within the established Navi Mumbai clusters faces a ceiling that permitting reform alone cannot resolve.link链接
Power电力The government's position differs: MeitY told Parliament that the national transmission system is adequately prepared to supply power reliably across regions.政府的立场不同:MeitY 向议会表示,全国输电系统已做好充分准备,可在各地区可靠供电。statement (government)声明(政府)2026-03-13India’s national transmission infrastructure is continuously being expanded to meet growing electricity demand. It is adequately prepared to ensure reliable power supply across regions.link链接
Power电力The CEA has set up a committee on how large data centres affect the power system and grid stability, after Odisha raised concerns about large collective power purchases by operators, according to a KNN report that cites the Economic Times.据 KNN 援引《经济时报》报道,在奥里萨邦就运营商大规模集体购电表达担忧后,CEA 成立了委员会,研究大型数据中心对电力系统和电网稳定的影响。actual实际2026-10-01The immediate trigger for the committee was concerns raised by Odisha over grid-linked operational challenges arising from large collective power purchases by data centre operators, reported Economic Times.link链接
Power电力A market report says the 26.3 GW covers 11 states, that developers have applied for grid connectivity for about 17 GW of it, and that applications for the remaining 9.3 GW are still pending. If correct, this could link the 17 GW and 26.3 GW figures, but no ministry document stating it was found.一份市场报道称,26.3 GW 覆盖 11 个邦,开发商已就其中约 17 GW 申请并网,其余 9.3 GW 的申请仍未完成。如果属实,这可能解释 17 GW 与 26.3 GW 的关系,但未找到说明这一点的部委文件。actual实际2026-08-27The Ministry of Power now expects them to add 26.3 GW of load across 11 states. Developers have already applied for grid connectivity covering around 17 GW of that, while applications for the remaining 9.3 GW are still pending.link链接
Water水The water ministry (Jal Shakti) told Parliament that MeitY has received no concerns about data-centre water use, and that groundwater extraction is controlled by general guidelines (S.O. 3289(E) of 24 September 2020, amended 29 March 2023). The reply gives no water limit or WUE requirement for data centres.水利部(Jal Shakti)向议会表示,MeitY 未收到有关数据中心用水的关切;地下水开采由一般性指南管理(2020 年 9 月 24 日 S.O. 3289(E),2023 年 3 月 29 日修订)。答复未给出针对数据中心的用水限值或 WUE 要求。in force生效中2026-03-30The Ministry of Electronics & Information Technology (MeitY) reported that no concerns have been received regarding water consumption in Data Centres. … for regulation & control ground water extraction, guidelines have been issued by Ministry of Jal Shakti vide notification no. S.O. 3289(E) dated 24.09.2020 & amendment notification dated 29.03.2023.link链接
Water水Newslaundry reports that the Central Ground Water Board found Bengaluru extracts almost 10 times what it recharges each year, and that Devanahalli, which hosts several data centres, uses 169% of permissible extraction. It also reports Karnataka's IT minister telling the Assembly that each MW needs 25 million litres of water a year.据 Newslaundry 报道,中央地下水委员会发现班加罗尔每年的地下水开采量几乎是补给量的 10 倍;有多个数据中心的 Devanahalli 开采量达到允许开采量的 169%。报道还称,卡纳塔克邦 IT 部长在邦议会表示,每 MW 每年需要 2,500 万升水。actual实际2026-04-16The Central Ground Water Board has found that Bengaluru extracts almost 10 times the water it recharges each year. Devanahalli, which has no perennial surface water source and hosts multiple data centres, consumes 169% of permissible extraction limits of water.link链接
Water水Down To Earth reports that Chennai nearly ran out of water in 2019 and brought in supplies by train, and that the city still relies heavily on erratic rains, desalination plants and groundwater.据 Down To Earth 报道,金奈 2019 年几乎断水,曾用火车运水;该市至今仍严重依赖不稳定的降雨、海水淡化厂和地下水。actual实际2026-07-04In 2019, the city nearly ran out of water and had to ship in supplies by train from afar, narrowly missing what was called “Day Zero.” Successive monsoons have raised storage levels but Chennai continues to rely heavily on erratic rains, desalination plants and extraction of ground water.link链接
Water水The Andhra Pradesh High Court refused to stay construction of the Google-Adani data centre at Visakhapatnam, while questioning its environmental clearance and its proposed water and electricity use, according to a legal news report.据法律新闻报道,安得拉邦高等法院拒绝叫停维沙卡帕特南的 Google-Adani 数据中心施工,同时质询其环境许可以及拟议的用水和用电。actual实际2026-08-24The Andhra Pradesh High Court has refused to stay the construction of Google-Adani’s proposed $15 billion data centre in Visakhapatnam, even as it questioned the State government over the approvals granted for the project.link链接
Water水Karnataka's Sustainable Data Centre Policy 2026-31, as reported, reimburses 100% of water charges, up to Rs 30 lakh a year for two years, for data-centre units at a WUE of 0.7 to 1.3 litres per kWh held for at least three years. A separate measure reimburses treated-water charges, up to Rs 8 lakh a year for five years.据报道,卡纳塔克邦《2026-31 可持续数据中心政策》对 WUE 为 0.7 至 1.3 L/kWh 且保持至少三年的数据中心项目,报销 100% 水费,每年最高 300 万卢比(Rs 30 lakh),为期两年。另一项措施报销再生水费用,每年最高 80 万卢比(Rs 8 lakh),为期五年。condition of state incentives邦级激励条件2026-09-30A separate WUE-linked incentive provides reimbursement of 100% of water charges, up to Rs 30 lakh per year for two consecutive years, for eligible units that achieve a WUE between 0.7 and 1.3 litres per kWh and maintain the specified performance level for at least three consecutive years.link链接
Water水Uttar Pradesh's Data Centre Policy 2026 says operators shall adopt water-efficient cooling, closed-loop systems and treated-wastewater reuse, and that water availability is assessed before land is allocated in state-agency areas. It sets no WUE figure.北方邦《2026 数据中心政策》规定,运营商须采用节水冷却、闭式系统和再生水回用;在邦属机构辖区,分配土地前须评估水源条件。政策未设定 WUE 数值。in force (policy)生效(政策)2026-07Data Centre players shall adopt water -efficient cooling solutions, closed -loop systems, and treated wastewater reuse to reduce freshwater dependency.link链接
Efficiency rules能效要求Uttar Pradesh's Data Centre Policy 2026 sets no PUE limit. It raises subsidy ceilings in three PUE tiers (up to 1.35, 1.35 to 1.45, 1.45 to 1.60) for parks and units with a top-two green data-centre certification. At PUE up to 1.35, a park's overall interest-subsidy ceiling rises by ₹4 crore and its annual ceiling by ₹0.8 crore.北方邦《2026 数据中心政策》未设定 PUE 限值。对获得前两级绿色数据中心认证的园区和单体项目,按三档 PUE(不超过 1.35、1.35 至 1.45、1.45 至 1.60)提高补贴上限。PUE 不超过 1.35 时,园区的利息补贴总上限提高 4,000 万卢比(₹4 crore),年度上限提高 800 万卢比(₹0.8 crore)。condition of state incentives邦级激励条件2026-07PUE ≤ 1.35 4 0.8 … 1.35 < PUE ≤ 1.45 2 0.6 … 1.45 < PUE ≤ 1.60 1 0.4link链接
Efficiency rules能效要求Karnataka's Sustainable Data Centre Policy 2026-31, as reported, targets 1 GW of IT load by 2031, requires plant-wise reporting of PUE and WUE, and pays Rs 20 crore once to units reaching PUE 1.00 to 1.20, after they hold it for three consecutive years.据报道,卡纳塔克邦《2026-31 可持续数据中心政策》目标是到 2031 年达到 1 GW IT 负荷,要求按站点报告 PUE 和 WUE,并向 PUE 达到 1.00 至 1.20 且连续保持三年的数据中心项目一次性支付 2 亿卢比(Rs 20 crore)。condition of state incentives邦级激励条件2026-09-30Data centres will have to report Power Usage Effectiveness (PUE) and Water Usage Effectiveness (WUE) on a plant-wise basis. … Units achieving a PUE of 1.00 to 1.20 can receive Rs 20 crore as one-time financial support.link链接
Efficiency rules能效要求MeitY told Parliament that the Bureau of Indian Standards has published standards on PUE, CUE, CER and WUE, and that the Bureau of Energy Efficiency's building codes (ECBC 2017, ECSBC 2024) include provisions relevant to data centres. The reply sets no PUE or WUE limit and does not say whether the standards are mandatory.MeitY 向议会表示,印度标准局已发布 PUE、CUE、CER 和 WUE 标准,能效局的建筑规范(ECBC 2017、ECSBC 2024)含有与数据中心相关的条款。答复未设定 PUE 或 WUE 限值,也未说明这些标准是否强制。published standard已发布标准2026-08-07Bureau of Indian Standards (BIS), through technical committee LITD 31 (Cloud Computing, IT & Data Centres), has published a series of Indian Standards on Power Usage Effectiveness, Carbon Usage Effectiveness (CUE), Cooling Efficiency Ratio (CER), Water Usage Effectiveness (WUE) related to data centres.link链接
Policies政策MeitY's Data Centre Policy 2020 is marked as a draft for discussion. It proposes Data Centre Economic Zones, essential-service status and open access, and encourages renewable energy; the copy read sets no PUE or WUE figure.MeitY 的《2020 数据中心政策》标注为讨论稿。它提出设立数据中心经济区、赋予基本服务地位并实行开放接入,并鼓励可再生能源;所读副本未设定 PUE 或 WUE 数值。draft草案2020-11Data Centres to be declared as an Essential Service under “The Essential Services Maintenance Act, 1968 (ESMA)”link链接
Policies政策Data centres with at least 5 MW of IT load are on the Finance Ministry's Harmonized Master List of Infrastructure sub-sectors.IT 负荷不低于 5 MW 的数据中心列入财政部《基础设施子行业统一总清单》。in force生效中2022-10-11Data Centre housed in a dedicated/centralized building for storage and processing of digital data applications with a minimum capacity of 5 MW of IT load. Read from a reproduction of the Department of Economic Affairs notification of 11 October 2022 on TaxGuru; the ministry's own copy was not opened.读自 TaxGuru 转载的经济事务局 2022 年 10 月 11 日通知;未打开财政部自己的副本。link链接
Policies政策The Union Budget 2026-27 proposed a tax holiday until 2047 for a foreign company selling cloud services to customers globally using data-centre services from India; Indian customers must be served through an Indian reseller. The Budget memorandum limits it to data centres set up under an approved scheme, notified by MeitY, and owned and operated by an Indian company, and a 15% safe harbour on cost applies to a related Indian company. These texts contain no PUE or water condition.2026-27 联邦预算提议,外国公司利用印度的数据中心服务向全球客户销售云服务,可享受至 2047 年的免税期;服务印度客户须通过印度经销商。预算备忘录把范围限于按批准方案设立、经 MeitY 公告、由印度公司拥有和运营的数据中心;关联印度公司适用成本加 15% 的安全港。这些文本没有 PUE 或用水条件。in force from 2026-04-01自 2026-04-01 生效2026-02-01I propose to provide tax holiday till 2047 to any foreign company that provides cloud services to customers globally by using data centre services from India.link链接
Policies政策NITI Aayog's Data Centre Evaluation Framework is guidance for states, not regulation. It asks for a power plan validated jointly by developer, distribution company and state transmission utility; demand-response readiness above 20 MW; design and guaranteed PUE; standardised PUE, WUE and CUE measurement; and desalinated water where basin stress rules out more fresh water.NITI Aayog 的《数据中心评估框架》是给各邦的指引,不是法规。它要求开发商、配电公司和邦输电公司共同验证供电计划;20 MW 以上具备需求响应能力;提供设计和保证 PUE;统一 PUE、WUE 和 CUE 的计量;流域压力不允许再取淡水时使用淡化水。advice建议2026-10-14The framework is intended to support decision-making, not prescribe a uniform approach or create an additional layer of regulation. … For facilities above 20 MW, require automated demand-response readiness … Where basin stress precludes additional freshwater abstraction, require desalinated water where feasiblelink链接
Policies政策Gujarat notified its Data Centre Policy 2026-29, planning 7.5 GW of capacity; eligible projects must source at least 51% of operational electricity from renewable and green sources. No PUE or WUE figure appears in the reports read.古吉拉特邦正式发布了《2026-29 数据中心政策》,计划 7.5 GW 容量;符合条件的项目,其运营用电须至少有 51% 来自可再生和绿色能源。所读报道中没有 PUE 或 WUE 数值。in force (policy)生效(政策)2026-08-07Eligible data centre projects will be required to source at least 51 per cent of their operational electricity consumption from renewable and green energy sourceslink链接
Policies政策Maharashtra widened its Integrated Green Data Centre Parks policy from three parks to twenty, statewide, and cut the required green-energy share for core activities from 100% to 51%, by a Government Resolution of 9 June 2026, according to a trade report.据行业报道,马哈拉施特拉邦以 2026 年 6 月 9 日的政府决议,把综合绿色数据中心园区政策从三个园区扩大到全邦二十个,并把核心活动的绿色能源比例要求从 100% 降至 51%。in force (policy)生效(政策)2026-06-09expanding the number of permitted parks from three to twenty and extending the scheme across the entire state. The changes were notified through a Government Resolution (GR) dated June 9, 2026. … The revised policy reduces the mandatory green energy usage requirement for core data center activities from 100% to 51%.link链接
Policies政策Andhra Pradesh's IT minister says at least 70% of the energy used by data centres must be renewable, and that water for the Visakhapatnam cluster is to come through the Polavaram project, with incentives for desalination.安得拉邦 IT 部长称,数据中心至少 70% 的能源须来自可再生能源;维沙卡帕特南集群的用水将经 Polavaram 工程供应,并对海水淡化提供激励。announced已宣布2026-09-25“The first thumb rule is that a minimum 70% of the energy used by data centres must come from renewable sources,” Lokesh saidlink链接
Policies政策India's Digital Personal Data Protection Rules 2025 let the central government require Significant Data Fiduciaries to keep specified personal data in India. Other personal data may leave India, subject to requirements the government may set on making it available to a foreign state. No general localisation duty was found in these rules.印度《2025 数字个人数据保护规则》允许中央政府要求重要数据受托人把指定的个人数据留在印度境内。其他个人数据可以出境,但政府可就向外国提供这些数据设定要求。这些规则中未发现一般性本地化义务。in force from 2027-05自 2027-05 生效2025-11-13A Significant Data Fiduciary shall undertake measures to ensure that personal data specified by the Central Government, on the basis of the recommendations of a committee constituted by it, is processed subject to the restriction that the personal data and the traffic data pertaining to its flow is not transferred outside the territory of India.link链接
Policies政策The National Green Tribunal flagged gaps in the clearance of a 512 MW data centre at Visakhapatnam, granted as a building project. It said public consultation and site-specific conditions were not taken into account, that heat generation appeared to be overlooked, that the environmental rules have no category for mega data centres, and that the 2020 draft policy was never finalised, according to LiveLaw.据 LiveLaw 报道,国家绿色法庭指出,维沙卡帕特南一个 512 MW 数据中心的环境许可存在缺口:它按建筑项目审批,未考虑公众咨询和场地特定条件,发热问题似被忽略;环境规定中没有超大型数据中心的类别,2020 年政策草案也未最终确定。actual实际2026-10-30It pointed out that the EIA Notification does not provide a specific category for mega data centre projects. The Tribunal further observed that India's Draft Data Centre Policy, 2020, had not been finalised.link链接
Policies政策The Green Energy Open Access Rules of 2022 let any consumer with a load of 100 kW or more, down from 1 MW, buy renewable power directly through the grid.2022 年《绿色能源开放接入规则》允许负荷 100 kW 及以上(此前为 1 MW)的任何用户通过电网直接购买可再生电力。in force生效中2022-06-06The Green Open Access is allowed to any consumer and the limit of Open Access Transaction has been reduced from 1 MW to 100 kW for green energylink链接
Projects项目Google with AdaniConneX and Airtel, Visakhapatnam, Andhra Pradesh安得拉邦维沙卡帕特南: US$15 billion investment (company figure, 2026-2030); a campus capable of gigawatt-scale compute投资 150 亿美元(公司数字,2026-2030 年);可达吉瓦级算力的园区investment投资2025-10-14the Visakhapatnam AI hub will include a purpose-built data center campus capable of gigawatt-scale compute capacity.link链接
Projects项目Vizag Hyperscale Data Centre Park (Adani Infra), Adavivaram and Mudasarlova, Visakhapatnam维沙卡帕特南 Adavivaram 和 Mudasarlova: 512 MW proposed; environmental clearance of 10 June 2026 under challenge at the National Green Tribunal拟建 512 MW;2026 年 6 月 10 日的环境许可正在国家绿色法庭受到质疑capacity容量2026-10-30The clearance was granted for a proposed 512 MW data centre at Adavivaram and Mudasarlova villages in Andhra Pradesh.link链接
Projects项目Reliance Industries, Jamnagar, Gujarat古吉拉特邦贾姆纳加尔: first 120 MW of AI compute due by the end of 2026, as reported from the annual meeting首批 120 MW AI 算力计划于 2026 年底投运,据年度股东大会报道capacity容量2026-06-19The company said it will commission the first 120 megawatts (MW) of its AI compute infrastructure by the end of 2026.link链接
Projects项目TCS HyperVault with OpenAI, India; site not stated in the report read印度;所读报道未说明地点: 100 MW of AI-ready capacity, with an option to scale to 1 GW, as reported100 MW AI 就绪容量,可选择扩展至 1 GW,据报道capacity容量2026-02-19OpenAI will anchor Tata Consultancy Services’ (TCS) HyperVault data center platform with 100 MW of AI-ready capacity, with an option to scale to 1 gigawatt over timelink链接
Projects项目Microsoft, India; includes the India South Central region in Hyderabad印度;包括海得拉巴的 India South Central 区域: US$17.5 billion over CY2026-2029, covering infrastructure, skilling and operations, not capacity2026-2029 年 175 亿美元,涵盖基础设施、技能培训和运营,不是容量investment投资2025-12-09today we are announcing our largest investment in Asia — US$17.5 billion over four years (CY 2026 to 2029)link链接
Projects项目Amazon, India; AWS regions in Mumbai and Hyderabad印度;AWS 区域位于孟买和海得拉巴: more than US$35 billion through 2030 across all Amazon businesses, so not a data-centre figure至 2030 年超过 350 亿美元,覆盖亚马逊全部业务,因此不是数据中心数字investment投资2025-12-10Amazon has announced plans to invest more than US$ 35 billion across all its businesses in India through 2030link链接
Projects项目Sify Infinit Spaces, Navi Mumbai and Chennai新孟买和金奈: 103 MW across two data centres, financed with the International Finance Corporation两个数据中心共 103 MW,由国际金融公司提供融资capacity容量2026-06-24The funding will support the development of two data centres in Navi Mumbai and Chennai with a combined capacity of 103 megawatt (MW).link链接
Projects项目Yotta, Greater Noida, Uttar Pradesh北方邦大诺伊达: campus at 60 MW today, able to expand to 250 MW, as reported; more than US$2 billion for an NVIDIA AI hub园区目前 60 MW,可扩展至 250 MW,据报道;超过 20 亿美元用于 NVIDIA AI 中心 (liquid cooling, as reported液冷,据报道)capacity容量2026-02-18The Greater Noida campus currently has a 60 MW capacity and can expand to 250 MW in the future.link链接
Projects项目Yotta (in Hiranandani Fortune City), Panvel, Navi Mumbai新孟买 Panvel: NM1: 52 MW of IT power, with more buildings possible on the campusNM1:52 MW IT 负荷,园区还可增加建筑 (design PUE 1.4 (company figure)设计 PUE 1.4(公司数字))capacity容量2026-11-06Located in the 600-acre Hiranandani Fortune City, Yotta Data Center Park at Panvel has Yotta NM1, its first data centerlink链接
Projects项目Lodha Developers, Palava/Ambernath, Thane district, as reported塔那县 Palava/Ambernath(据报道): Rs 30,000 crore memorandum with Maharashtra for a green data-centre park; an agreement, not capacity与马哈拉施特拉邦签署 3,000 亿卢比(Rs 30,000 crore)绿色数据中心园区备忘录;是协议,不是容量investment投资2025-09-11The total investment in this project is planned to be Rs 30,000 crore.link链接
Climate气候Mumbai (Chhatrapati Shivaji Airport)孟买(贾特拉帕蒂·希瓦吉机场) (43003099999), W17 at 5 K: 0 hours a year; single years 0–0; lowest-year coverage 95%、5 K:每年 0 小时;单年 0–0;最低单年覆盖率 95%computed by this site本站计算2020–2024NOAA
Climate气候Mumbai (Chhatrapati Shivaji Airport)孟买(贾特拉帕蒂·希瓦吉机场) (43003099999), W17 at 10 K: 0 hours a year; single years 0–0; lowest-year coverage 95%、10 K:每年 0 小时;单年 0–0;最低单年覆盖率 95%computed by this site本站计算2020–2024NOAA
Climate气候Mumbai (Chhatrapati Shivaji Airport)孟买(贾特拉帕蒂·希瓦吉机场) (43003099999), W17 at 15 K: 0 hours a year; single years 0–0; lowest-year coverage 95%、15 K:每年 0 小时;单年 0–0;最低单年覆盖率 95%computed by this site本站计算2020–2024NOAA
Climate气候Mumbai (Chhatrapati Shivaji Airport)孟买(贾特拉帕蒂·希瓦吉机场) (43003099999), W20 at 5 K: 2 hours a year; single years 0–5; lowest-year coverage 95%、5 K:每年 2 小时;单年 0–5;最低单年覆盖率 95%computed by this site本站计算2020–2024NOAA
Climate气候Mumbai (Chhatrapati Shivaji Airport)孟买(贾特拉帕蒂·希瓦吉机场) (43003099999), W20 at 10 K: 0 hours a year; single years 0–0; lowest-year coverage 95%、10 K:每年 0 小时;单年 0–0;最低单年覆盖率 95%computed by this site本站计算2020–2024NOAA
Climate气候Mumbai (Chhatrapati Shivaji Airport)孟买(贾特拉帕蒂·希瓦吉机场) (43003099999), W20 at 15 K: 0 hours a year; single years 0–0; lowest-year coverage 95%、15 K:每年 0 小时;单年 0–0;最低单年覆盖率 95%computed by this site本站计算2020–2024NOAA
Climate气候Mumbai (Chhatrapati Shivaji Airport)孟买(贾特拉帕蒂·希瓦吉机场) (43003099999), W25 at 5 K: 130 hours a year; single years 96–181; lowest-year coverage 95%、5 K:每年 130 小时;单年 96–181;最低单年覆盖率 95%computed by this site本站计算2020–2024NOAA
Climate气候Mumbai (Chhatrapati Shivaji Airport)孟买(贾特拉帕蒂·希瓦吉机场) (43003099999), W25 at 10 K: 2 hours a year; single years 0–5; lowest-year coverage 95%、10 K:每年 2 小时;单年 0–5;最低单年覆盖率 95%computed by this site本站计算2020–2024NOAA
Climate气候Mumbai (Chhatrapati Shivaji Airport)孟买(贾特拉帕蒂·希瓦吉机场) (43003099999), W25 at 15 K: 0 hours a year; single years 0–0; lowest-year coverage 95%、15 K:每年 0 小时;单年 0–0;最低单年覆盖率 95%computed by this site本站计算2020–2024NOAA
Climate气候Mumbai (Chhatrapati Shivaji Airport)孟买(贾特拉帕蒂·希瓦吉机场) (43003099999), W32 at 5 K: 3,093 hours a year; single years 2,685–3,377; lowest-year coverage 95%、5 K:每年 3,093 小时;单年 2,685–3,377;最低单年覆盖率 95%computed by this site本站计算2020–2024NOAA
Climate气候Mumbai (Chhatrapati Shivaji Airport)孟买(贾特拉帕蒂·希瓦吉机场) (43003099999), W32 at 10 K: 372 hours a year; single years 283–503; lowest-year coverage 95%、10 K:每年 372 小时;单年 283–503;最低单年覆盖率 95%computed by this site本站计算2020–2024NOAA
Climate气候Mumbai (Chhatrapati Shivaji Airport)孟买(贾特拉帕蒂·希瓦吉机场) (43003099999), W32 at 15 K: 16 hours a year; single years 4–25; lowest-year coverage 95%、15 K:每年 16 小时;单年 4–25;最低单年覆盖率 95%computed by this site本站计算2020–2024NOAA
Climate气候Mumbai (Chhatrapati Shivaji Airport)孟买(贾特拉帕蒂·希瓦吉机场) (43003099999), W40 at 5 K: 8,675 hours a year; single years 8,633–8,733; lowest-year coverage 95%、5 K:每年 8,675 小时;单年 8,633–8,733;最低单年覆盖率 95%computed by this site本站计算2020–2024NOAA
Climate气候Mumbai (Chhatrapati Shivaji Airport)孟买(贾特拉帕蒂·希瓦吉机场) (43003099999), W40 at 10 K: 6,516 hours a year; single years 6,275–6,675; lowest-year coverage 95%、10 K:每年 6,516 小时;单年 6,275–6,675;最低单年覆盖率 95%computed by this site本站计算2020–2024NOAA
Climate气候Mumbai (Chhatrapati Shivaji Airport)孟买(贾特拉帕蒂·希瓦吉机场) (43003099999), W40 at 15 K: 1,270 hours a year; single years 1,044–1,542; lowest-year coverage 95%、15 K:每年 1,270 小时;单年 1,044–1,542;最低单年覆盖率 95%computed by this site本站计算2020–2024NOAA
Climate气候Mumbai (Chhatrapati Shivaji Airport)孟买(贾特拉帕蒂·希瓦吉机场) (43003099999), W41 at 5 K: 8,725 hours a year; single years 8,711–8,750; lowest-year coverage 95%、5 K:每年 8,725 小时;单年 8,711–8,750;最低单年覆盖率 95%computed by this site本站计算2020–2024NOAA
Climate气候Mumbai (Chhatrapati Shivaji Airport)孟买(贾特拉帕蒂·希瓦吉机场) (43003099999), W41 at 10 K: 7,284 hours a year; single years 7,109–7,396; lowest-year coverage 95%、10 K:每年 7,284 小时;单年 7,109–7,396;最低单年覆盖率 95%computed by this site本站计算2020–2024NOAA
Climate气候Mumbai (Chhatrapati Shivaji Airport)孟买(贾特拉帕蒂·希瓦吉机场) (43003099999), W41 at 15 K: 2,010 hours a year; single years 1,710–2,269; lowest-year coverage 95%、15 K:每年 2,010 小时;单年 1,710–2,269;最低单年覆盖率 95%computed by this site本站计算2020–2024NOAA
Climate气候Mumbai (Chhatrapati Shivaji Airport)孟买(贾特拉帕蒂·希瓦吉机场) (43003099999), W45 at 5 K: 8,760 hours a year; single years 8,758–8,760; lowest-year coverage 95%、5 K:每年 8,760 小时;单年 8,758–8,760;最低单年覆盖率 95%computed by this site本站计算2020–2024NOAA
Climate气候Mumbai (Chhatrapati Shivaji Airport)孟买(贾特拉帕蒂·希瓦吉机场) (43003099999), W45 at 10 K: 8,675 hours a year; single years 8,633–8,733; lowest-year coverage 95%、10 K:每年 8,675 小时;单年 8,633–8,733;最低单年覆盖率 95%computed by this site本站计算2020–2024NOAA
Climate气候Mumbai (Chhatrapati Shivaji Airport)孟买(贾特拉帕蒂·希瓦吉机场) (43003099999), W45 at 15 K: 6,516 hours a year; single years 6,275–6,675; lowest-year coverage 95%、15 K:每年 6,516 小时;单年 6,275–6,675;最低单年覆盖率 95%computed by this site本站计算2020–2024NOAA
Climate气候Chennai (Chennai Airport)金奈(金奈机场) (43279099999), W17 at 5 K: 0 hours a year; single years 0–0; lowest-year coverage 96%、5 K:每年 0 小时;单年 0–0;最低单年覆盖率 96%computed by this site本站计算2020–2024NOAA
Climate气候Chennai (Chennai Airport)金奈(金奈机场) (43279099999), W17 at 10 K: 0 hours a year; single years 0–0; lowest-year coverage 96%、10 K:每年 0 小时;单年 0–0;最低单年覆盖率 96%computed by this site本站计算2020–2024NOAA
Climate气候Chennai (Chennai Airport)金奈(金奈机场) (43279099999), W17 at 15 K: 0 hours a year; single years 0–0; lowest-year coverage 96%、15 K:每年 0 小时;单年 0–0;最低单年覆盖率 96%computed by this site本站计算2020–2024NOAA
Climate气候Chennai (Chennai Airport)金奈(金奈机场) (43279099999), W20 at 5 K: 0 hours a year; single years 0–0; lowest-year coverage 96%、5 K:每年 0 小时;单年 0–0;最低单年覆盖率 96%computed by this site本站计算2020–2024NOAA
Climate气候Chennai (Chennai Airport)金奈(金奈机场) (43279099999), W20 at 10 K: 0 hours a year; single years 0–0; lowest-year coverage 96%、10 K:每年 0 小时;单年 0–0;最低单年覆盖率 96%computed by this site本站计算2020–2024NOAA
Climate气候Chennai (Chennai Airport)金奈(金奈机场) (43279099999), W20 at 15 K: 0 hours a year; single years 0–0; lowest-year coverage 96%、15 K:每年 0 小时;单年 0–0;最低单年覆盖率 96%computed by this site本站计算2020–2024NOAA
Climate气候Chennai (Chennai Airport)金奈(金奈机场) (43279099999), W25 at 5 K: 4 hours a year; single years 0–12; lowest-year coverage 96%、5 K:每年 4 小时;单年 0–12;最低单年覆盖率 96%computed by this site本站计算2020–2024NOAA
Climate气候Chennai (Chennai Airport)金奈(金奈机场) (43279099999), W25 at 10 K: 0 hours a year; single years 0–0; lowest-year coverage 96%、10 K:每年 0 小时;单年 0–0;最低单年覆盖率 96%computed by this site本站计算2020–2024NOAA
Climate气候Chennai (Chennai Airport)金奈(金奈机场) (43279099999), W25 at 15 K: 0 hours a year; single years 0–0; lowest-year coverage 96%、15 K:每年 0 小时;单年 0–0;最低单年覆盖率 96%computed by this site本站计算2020–2024NOAA
Climate气候Chennai (Chennai Airport)金奈(金奈机场) (43279099999), W32 at 5 K: 2,773 hours a year; single years 2,481–3,026; lowest-year coverage 96%、5 K:每年 2,773 小时;单年 2,481–3,026;最低单年覆盖率 96%computed by this site本站计算2020–2024NOAA
Climate气候Chennai (Chennai Airport)金奈(金奈机场) (43279099999), W32 at 10 K: 103 hours a year; single years 18–178; lowest-year coverage 96%、10 K:每年 103 小时;单年 18–178;最低单年覆盖率 96%computed by this site本站计算2020–2024NOAA
Climate气候Chennai (Chennai Airport)金奈(金奈机场) (43279099999), W32 at 15 K: 0 hours a year; single years 0–0; lowest-year coverage 96%、15 K:每年 0 小时;单年 0–0;最低单年覆盖率 96%computed by this site本站计算2020–2024NOAA
Climate气候Chennai (Chennai Airport)金奈(金奈机场) (43279099999), W40 at 5 K: 8,402 hours a year; single years 8,339–8,451; lowest-year coverage 96%、5 K:每年 8,402 小时;单年 8,339–8,451;最低单年覆盖率 96%computed by this site本站计算2020–2024NOAA
Climate气候Chennai (Chennai Airport)金奈(金奈机场) (43279099999), W40 at 10 K: 5,901 hours a year; single years 5,626–6,143; lowest-year coverage 96%、10 K:每年 5,901 小时;单年 5,626–6,143;最低单年覆盖率 96%computed by this site本站计算2020–2024NOAA
Climate气候Chennai (Chennai Airport)金奈(金奈机场) (43279099999), W40 at 15 K: 1,129 hours a year; single years 885–1,279; lowest-year coverage 96%、15 K:每年 1,129 小时;单年 885–1,279;最低单年覆盖率 96%computed by this site本站计算2020–2024NOAA
Climate气候Chennai (Chennai Airport)金奈(金奈机场) (43279099999), W41 at 5 K: 8,571 hours a year; single years 8,501–8,627; lowest-year coverage 96%、5 K:每年 8,571 小时;单年 8,501–8,627;最低单年覆盖率 96%computed by this site本站计算2020–2024NOAA
Climate气候Chennai (Chennai Airport)金奈(金奈机场) (43279099999), W41 at 10 K: 6,712 hours a year; single years 6,519–6,824; lowest-year coverage 96%、10 K:每年 6,712 小时;单年 6,519–6,824;最低单年覆盖率 96%computed by this site本站计算2020–2024NOAA
Climate气候Chennai (Chennai Airport)金奈(金奈机场) (43279099999), W41 at 15 K: 1,907 hours a year; single years 1,613–2,149; lowest-year coverage 96%、15 K:每年 1,907 小时;单年 1,613–2,149;最低单年覆盖率 96%computed by this site本站计算2020–2024NOAA
Climate气候Chennai (Chennai Airport)金奈(金奈机场) (43279099999), W45 at 5 K: 8,754 hours a year; single years 8,748–8,760; lowest-year coverage 96%、5 K:每年 8,754 小时;单年 8,748–8,760;最低单年覆盖率 96%computed by this site本站计算2020–2024NOAA
Climate气候Chennai (Chennai Airport)金奈(金奈机场) (43279099999), W45 at 10 K: 8,402 hours a year; single years 8,339–8,451; lowest-year coverage 96%、10 K:每年 8,402 小时;单年 8,339–8,451;最低单年覆盖率 96%computed by this site本站计算2020–2024NOAA
Climate气候Chennai (Chennai Airport)金奈(金奈机场) (43279099999), W45 at 15 K: 5,901 hours a year; single years 5,626–6,143; lowest-year coverage 96%、15 K:每年 5,901 小时;单年 5,626–6,143;最低单年覆盖率 96%computed by this site本站计算2020–2024NOAA
Climate气候Bengaluru (Kempegowda Airport)班加罗尔(肯佩戈达机场) (42705699999), W17 at 5 K: 4 hours a year; single years 0–15; lowest-year coverage 96%、5 K:每年 4 小时;单年 0–15;最低单年覆盖率 96%computed by this site本站计算2020–2024NOAA
Climate气候Bengaluru (Kempegowda Airport)班加罗尔(肯佩戈达机场) (42705699999), W17 at 10 K: 0 hours a year; single years 0–0; lowest-year coverage 96%、10 K:每年 0 小时;单年 0–0;最低单年覆盖率 96%computed by this site本站计算2020–2024NOAA
Climate气候Bengaluru (Kempegowda Airport)班加罗尔(肯佩戈达机场) (42705699999), W17 at 15 K: 0 hours a year; single years 0–0; lowest-year coverage 96%、15 K:每年 0 小时;单年 0–0;最低单年覆盖率 96%computed by this site本站计算2020–2024NOAA
Climate气候Bengaluru (Kempegowda Airport)班加罗尔(肯佩戈达机场) (42705699999), W20 at 5 K: 115 hours a year; single years 40–203; lowest-year coverage 96%、5 K:每年 115 小时;单年 40–203;最低单年覆盖率 96%computed by this site本站计算2020–2024NOAA
Climate气候Bengaluru (Kempegowda Airport)班加罗尔(肯佩戈达机场) (42705699999), W20 at 10 K: 0 hours a year; single years 0–2; lowest-year coverage 96%、10 K:每年 0 小时;单年 0–2;最低单年覆盖率 96%computed by this site本站计算2020–2024NOAA
Climate气候Bengaluru (Kempegowda Airport)班加罗尔(肯佩戈达机场) (42705699999), W20 at 15 K: 0 hours a year; single years 0–0; lowest-year coverage 96%、15 K:每年 0 小时;单年 0–0;最低单年覆盖率 96%computed by this site本站计算2020–2024NOAA
Climate气候Bengaluru (Kempegowda Airport)班加罗尔(肯佩戈达机场) (42705699999), W25 at 5 K: 1,681 hours a year; single years 1,279–2,001; lowest-year coverage 96%、5 K:每年 1,681 小时;单年 1,279–2,001;最低单年覆盖率 96%computed by this site本站计算2020–2024NOAA
Climate气候Bengaluru (Kempegowda Airport)班加罗尔(肯佩戈达机场) (42705699999), W25 at 10 K: 115 hours a year; single years 40–203; lowest-year coverage 96%、10 K:每年 115 小时;单年 40–203;最低单年覆盖率 96%computed by this site本站计算2020–2024NOAA
Climate气候Bengaluru (Kempegowda Airport)班加罗尔(肯佩戈达机场) (42705699999), W25 at 15 K: 0 hours a year; single years 0–2; lowest-year coverage 96%、15 K:每年 0 小时;单年 0–2;最低单年覆盖率 96%computed by this site本站计算2020–2024NOAA
Climate气候Bengaluru (Kempegowda Airport)班加罗尔(肯佩戈达机场) (42705699999), W32 at 5 K: 7,220 hours a year; single years 7,040–7,494; lowest-year coverage 96%、5 K:每年 7,220 小时;单年 7,040–7,494;最低单年覆盖率 96%computed by this site本站计算2020–2024NOAA
Climate气候Bengaluru (Kempegowda Airport)班加罗尔(肯佩戈达机场) (42705699999), W32 at 10 K: 3,803 hours a year; single years 3,474–4,131; lowest-year coverage 96%、10 K:每年 3,803 小时;单年 3,474–4,131;最低单年覆盖率 96%computed by this site本站计算2020–2024NOAA
Climate气候Bengaluru (Kempegowda Airport)班加罗尔(肯佩戈达机场) (42705699999), W32 at 15 K: 430 hours a year; single years 240–584; lowest-year coverage 96%、15 K:每年 430 小时;单年 240–584;最低单年覆盖率 96%computed by this site本站计算2020–2024NOAA
Climate气候Bengaluru (Kempegowda Airport)班加罗尔(肯佩戈达机场) (42705699999), W40 at 5 K: 8,746 hours a year; single years 8,691–8,760; lowest-year coverage 96%、5 K:每年 8,746 小时;单年 8,691–8,760;最低单年覆盖率 96%computed by this site本站计算2020–2024NOAA
Climate气候Bengaluru (Kempegowda Airport)班加罗尔(肯佩戈达机场) (42705699999), W40 at 10 K: 8,270 hours a year; single years 8,118–8,381; lowest-year coverage 96%、10 K:每年 8,270 小时;单年 8,118–8,381;最低单年覆盖率 96%computed by this site本站计算2020–2024NOAA
Climate气候Bengaluru (Kempegowda Airport)班加罗尔(肯佩戈达机场) (42705699999), W40 at 15 K: 6,021 hours a year; single years 5,764–6,275; lowest-year coverage 96%、15 K:每年 6,021 小时;单年 5,764–6,275;最低单年覆盖率 96%computed by this site本站计算2020–2024NOAA
Climate气候Bengaluru (Kempegowda Airport)班加罗尔(肯佩戈达机场) (42705699999), W41 at 5 K: 8,755 hours a year; single years 8,736–8,760; lowest-year coverage 96%、5 K:每年 8,755 小时;单年 8,736–8,760;最低单年覆盖率 96%computed by this site本站计算2020–2024NOAA
Climate气候Bengaluru (Kempegowda Airport)班加罗尔(肯佩戈达机场) (42705699999), W41 at 10 K: 8,440 hours a year; single years 8,292–8,532; lowest-year coverage 96%、10 K:每年 8,440 小时;单年 8,292–8,532;最低单年覆盖率 96%computed by this site本站计算2020–2024NOAA
Climate气候Bengaluru (Kempegowda Airport)班加罗尔(肯佩戈达机场) (42705699999), W41 at 15 K: 6,637 hours a year; single years 6,408–6,895; lowest-year coverage 96%、15 K:每年 6,637 小时;单年 6,408–6,895;最低单年覆盖率 96%computed by this site本站计算2020–2024NOAA
Climate气候Bengaluru (Kempegowda Airport)班加罗尔(肯佩戈达机场) (42705699999), W45 at 5 K: 8,760 hours a year; single years 8,760–8,760; lowest-year coverage 96%、5 K:每年 8,760 小时;单年 8,760–8,760;最低单年覆盖率 96%computed by this site本站计算2020–2024NOAA
Climate气候Bengaluru (Kempegowda Airport)班加罗尔(肯佩戈达机场) (42705699999), W45 at 10 K: 8,746 hours a year; single years 8,691–8,760; lowest-year coverage 96%、10 K:每年 8,746 小时;单年 8,691–8,760;最低单年覆盖率 96%computed by this site本站计算2020–2024NOAA
Climate气候Bengaluru (Kempegowda Airport)班加罗尔(肯佩戈达机场) (42705699999), W45 at 15 K: 8,270 hours a year; single years 8,118–8,381; lowest-year coverage 96%、15 K:每年 8,270 小时;单年 8,118–8,381;最低单年覆盖率 96%computed by this site本站计算2020–2024NOAA
Climate气候Hyderabad (Rajiv Gandhi Airport)海得拉巴(拉吉夫·甘地机场) (43128599999), W17 at 5 K: 6 hours a year; single years 0–20; lowest-year coverage 95%、5 K:每年 6 小时;单年 0–20;最低单年覆盖率 95%computed by this site本站计算2020–2024NOAA
Climate气候Hyderabad (Rajiv Gandhi Airport)海得拉巴(拉吉夫·甘地机场) (43128599999), W17 at 10 K: 0 hours a year; single years 0–0; lowest-year coverage 95%、10 K:每年 0 小时;单年 0–0;最低单年覆盖率 95%computed by this site本站计算2020–2024NOAA
Climate气候Hyderabad (Rajiv Gandhi Airport)海得拉巴(拉吉夫·甘地机场) (43128599999), W17 at 15 K: 0 hours a year; single years 0–0; lowest-year coverage 95%、15 K:每年 0 小时;单年 0–0;最低单年覆盖率 95%computed by this site本站计算2020–2024NOAA
Climate气候Hyderabad (Rajiv Gandhi Airport)海得拉巴(拉吉夫·甘地机场) (43128599999), W20 at 5 K: 60 hours a year; single years 40–114; lowest-year coverage 95%、5 K:每年 60 小时;单年 40–114;最低单年覆盖率 95%computed by this site本站计算2020–2024NOAA
Climate气候Hyderabad (Rajiv Gandhi Airport)海得拉巴(拉吉夫·甘地机场) (43128599999), W20 at 10 K: 2 hours a year; single years 0–6; lowest-year coverage 95%、10 K:每年 2 小时;单年 0–6;最低单年覆盖率 95%computed by this site本站计算2020–2024NOAA
Climate气候Hyderabad (Rajiv Gandhi Airport)海得拉巴(拉吉夫·甘地机场) (43128599999), W20 at 15 K: 0 hours a year; single years 0–0; lowest-year coverage 95%、15 K:每年 0 小时;单年 0–0;最低单年覆盖率 95%computed by this site本站计算2020–2024NOAA
Climate气候Hyderabad (Rajiv Gandhi Airport)海得拉巴(拉吉夫·甘地机场) (43128599999), W25 at 5 K: 963 hours a year; single years 793–1,079; lowest-year coverage 95%、5 K:每年 963 小时;单年 793–1,079;最低单年覆盖率 95%computed by this site本站计算2020–2024NOAA
Climate气候Hyderabad (Rajiv Gandhi Airport)海得拉巴(拉吉夫·甘地机场) (43128599999), W25 at 10 K: 60 hours a year; single years 40–114; lowest-year coverage 95%、10 K:每年 60 小时;单年 40–114;最低单年覆盖率 95%computed by this site本站计算2020–2024NOAA
Climate气候Hyderabad (Rajiv Gandhi Airport)海得拉巴(拉吉夫·甘地机场) (43128599999), W25 at 15 K: 2 hours a year; single years 0–6; lowest-year coverage 95%、15 K:每年 2 小时;单年 0–6;最低单年覆盖率 95%computed by this site本站计算2020–2024NOAA
Climate气候Hyderabad (Rajiv Gandhi Airport)海得拉巴(拉吉夫·甘地机场) (43128599999), W32 at 5 K: 5,746 hours a year; single years 5,612–5,792; lowest-year coverage 95%、5 K:每年 5,746 小时;单年 5,612–5,792;最低单年覆盖率 95%computed by this site本站计算2020–2024NOAA
Climate气候Hyderabad (Rajiv Gandhi Airport)海得拉巴(拉吉夫·甘地机场) (43128599999), W32 at 10 K: 1,860 hours a year; single years 1,619–2,008; lowest-year coverage 95%、10 K:每年 1,860 小时;单年 1,619–2,008;最低单年覆盖率 95%computed by this site本站计算2020–2024NOAA
Climate气候Hyderabad (Rajiv Gandhi Airport)海得拉巴(拉吉夫·甘地机场) (43128599999), W32 at 15 K: 232 hours a year; single years 168–340; lowest-year coverage 95%、15 K:每年 232 小时;单年 168–340;最低单年覆盖率 95%computed by this site本站计算2020–2024NOAA
Climate气候Hyderabad (Rajiv Gandhi Airport)海得拉巴(拉吉夫·甘地机场) (43128599999), W40 at 5 K: 8,484 hours a year; single years 8,422–8,562; lowest-year coverage 95%、5 K:每年 8,484 小时;单年 8,422–8,562;最低单年覆盖率 95%computed by this site本站计算2020–2024NOAA
Climate气候Hyderabad (Rajiv Gandhi Airport)海得拉巴(拉吉夫·甘地机场) (43128599999), W40 at 10 K: 7,401 hours a year; single years 7,270–7,463; lowest-year coverage 95%、10 K:每年 7,401 小时;单年 7,270–7,463;最低单年覆盖率 95%computed by this site本站计算2020–2024NOAA
Climate气候Hyderabad (Rajiv Gandhi Airport)海得拉巴(拉吉夫·甘地机场) (43128599999), W40 at 15 K: 4,433 hours a year; single years 4,198–4,524; lowest-year coverage 95%、15 K:每年 4,433 小时;单年 4,198–4,524;最低单年覆盖率 95%computed by this site本站计算2020–2024NOAA
Climate气候Hyderabad (Rajiv Gandhi Airport)海得拉巴(拉吉夫·甘地机场) (43128599999), W41 at 5 K: 8,594 hours a year; single years 8,517–8,658; lowest-year coverage 95%、5 K:每年 8,594 小时;单年 8,517–8,658;最低单年覆盖率 95%computed by this site本站计算2020–2024NOAA
Climate气候Hyderabad (Rajiv Gandhi Airport)海得拉巴(拉吉夫·甘地机场) (43128599999), W41 at 10 K: 7,755 hours a year; single years 7,653–7,832; lowest-year coverage 95%、10 K:每年 7,755 小时;单年 7,653–7,832;最低单年覆盖率 95%computed by this site本站计算2020–2024NOAA
Climate气候Hyderabad (Rajiv Gandhi Airport)海得拉巴(拉吉夫·甘地机场) (43128599999), W41 at 15 K: 5,108 hours a year; single years 4,939–5,184; lowest-year coverage 95%、15 K:每年 5,108 小时;单年 4,939–5,184;最低单年覆盖率 95%computed by this site本站计算2020–2024NOAA
Climate气候Hyderabad (Rajiv Gandhi Airport)海得拉巴(拉吉夫·甘地机场) (43128599999), W45 at 5 K: 8,754 hours a year; single years 8,740–8,760; lowest-year coverage 95%、5 K:每年 8,754 小时;单年 8,740–8,760;最低单年覆盖率 95%computed by this site本站计算2020–2024NOAA
Climate气候Hyderabad (Rajiv Gandhi Airport)海得拉巴(拉吉夫·甘地机场) (43128599999), W45 at 10 K: 8,484 hours a year; single years 8,422–8,562; lowest-year coverage 95%、10 K:每年 8,484 小时;单年 8,422–8,562;最低单年覆盖率 95%computed by this site本站计算2020–2024NOAA
Climate气候Hyderabad (Rajiv Gandhi Airport)海得拉巴(拉吉夫·甘地机场) (43128599999), W45 at 15 K: 7,401 hours a year; single years 7,270–7,463; lowest-year coverage 95%、15 K:每年 7,401 小时;单年 7,270–7,463;最低单年覆盖率 95%computed by this site本站计算2020–2024NOAA
Climate气候Visakhapatnam (Visakhapatnam Airport)维沙卡帕特南(维沙卡帕特南机场) (43149099999), W17 at 5 K: 0 hours a year; single years 0–0; lowest-year coverage 87%、5 K:每年 0 小时;单年 0–0;最低单年覆盖率 87%computed by this site本站计算2020–2024NOAA
Climate气候Visakhapatnam (Visakhapatnam Airport)维沙卡帕特南(维沙卡帕特南机场) (43149099999), W17 at 10 K: 0 hours a year; single years 0–0; lowest-year coverage 87%、10 K:每年 0 小时;单年 0–0;最低单年覆盖率 87%computed by this site本站计算2020–2024NOAA
Climate气候Visakhapatnam (Visakhapatnam Airport)维沙卡帕特南(维沙卡帕特南机场) (43149099999), W17 at 15 K: 0 hours a year; single years 0–0; lowest-year coverage 87%、15 K:每年 0 小时;单年 0–0;最低单年覆盖率 87%computed by this site本站计算2020–2024NOAA
Climate气候Visakhapatnam (Visakhapatnam Airport)维沙卡帕特南(维沙卡帕特南机场) (43149099999), W20 at 5 K: 6 hours a year; single years 0–18; lowest-year coverage 87%、5 K:每年 6 小时;单年 0–18;最低单年覆盖率 87%computed by this site本站计算2020–2024NOAA
Climate气候Visakhapatnam (Visakhapatnam Airport)维沙卡帕特南(维沙卡帕特南机场) (43149099999), W20 at 10 K: 0 hours a year; single years 0–0; lowest-year coverage 87%、10 K:每年 0 小时;单年 0–0;最低单年覆盖率 87%computed by this site本站计算2020–2024NOAA
Climate气候Visakhapatnam (Visakhapatnam Airport)维沙卡帕特南(维沙卡帕特南机场) (43149099999), W20 at 15 K: 0 hours a year; single years 0–0; lowest-year coverage 87%、15 K:每年 0 小时;单年 0–0;最低单年覆盖率 87%computed by this site本站计算2020–2024NOAA
Climate气候Visakhapatnam (Visakhapatnam Airport)维沙卡帕特南(维沙卡帕特南机场) (43149099999), W25 at 5 K: 323 hours a year; single years 208–402; lowest-year coverage 87%、5 K:每年 323 小时;单年 208–402;最低单年覆盖率 87%computed by this site本站计算2020–2024NOAA
Climate气候Visakhapatnam (Visakhapatnam Airport)维沙卡帕特南(维沙卡帕特南机场) (43149099999), W25 at 10 K: 6 hours a year; single years 0–18; lowest-year coverage 87%、10 K:每年 6 小时;单年 0–18;最低单年覆盖率 87%computed by this site本站计算2020–2024NOAA
Climate气候Visakhapatnam (Visakhapatnam Airport)维沙卡帕特南(维沙卡帕特南机场) (43149099999), W25 at 15 K: 0 hours a year; single years 0–0; lowest-year coverage 87%、15 K:每年 0 小时;单年 0–0;最低单年覆盖率 87%computed by this site本站计算2020–2024NOAA
Climate气候Visakhapatnam (Visakhapatnam Airport)维沙卡帕特南(维沙卡帕特南机场) (43149099999), W32 at 5 K: 3,787 hours a year; single years 3,454–3,974; lowest-year coverage 87%、5 K:每年 3,787 小时;单年 3,454–3,974;最低单年覆盖率 87%computed by this site本站计算2020–2024NOAA
Climate气候Visakhapatnam (Visakhapatnam Airport)维沙卡帕特南(维沙卡帕特南机场) (43149099999), W32 at 10 K: 739 hours a year; single years 560–837; lowest-year coverage 87%、10 K:每年 739 小时;单年 560–837;最低单年覆盖率 87%computed by this site本站计算2020–2024NOAA
Climate气候Visakhapatnam (Visakhapatnam Airport)维沙卡帕特南(维沙卡帕特南机场) (43149099999), W32 at 15 K: 41 hours a year; single years 1–93; lowest-year coverage 87%、15 K:每年 41 小时;单年 1–93;最低单年覆盖率 87%computed by this site本站计算2020–2024NOAA
Climate气候Visakhapatnam (Visakhapatnam Airport)维沙卡帕特南(维沙卡帕特南机场) (43149099999), W40 at 5 K: 8,617 hours a year; single years 8,492–8,697; lowest-year coverage 87%、5 K:每年 8,617 小时;单年 8,492–8,697;最低单年覆盖率 87%computed by this site本站计算2020–2024NOAA
Climate气候Visakhapatnam (Visakhapatnam Airport)维沙卡帕特南(维沙卡帕特南机场) (43149099999), W40 at 10 K: 6,611 hours a year; single years 6,352–6,856; lowest-year coverage 87%、10 K:每年 6,611 小时;单年 6,352–6,856;最低单年覆盖率 87%computed by this site本站计算2020–2024NOAA
Climate气候Visakhapatnam (Visakhapatnam Airport)维沙卡帕特南(维沙卡帕特南机场) (43149099999), W40 at 15 K: 1,962 hours a year; single years 1,713–2,164; lowest-year coverage 87%、15 K:每年 1,962 小时;单年 1,713–2,164;最低单年覆盖率 87%computed by this site本站计算2020–2024NOAA
Climate气候Visakhapatnam (Visakhapatnam Airport)维沙卡帕特南(维沙卡帕特南机场) (43149099999), W41 at 5 K: 8,695 hours a year; single years 8,600–8,738; lowest-year coverage 87%、5 K:每年 8,695 小时;单年 8,600–8,738;最低单年覆盖率 87%computed by this site本站计算2020–2024NOAA
Climate气候Visakhapatnam (Visakhapatnam Airport)维沙卡帕特南(维沙卡帕特南机场) (43149099999), W41 at 10 K: 7,253 hours a year; single years 6,994–7,476; lowest-year coverage 87%、10 K:每年 7,253 小时;单年 6,994–7,476;最低单年覆盖率 87%computed by this site本站计算2020–2024NOAA
Climate气候Visakhapatnam (Visakhapatnam Airport)维沙卡帕特南(维沙卡帕特南机场) (43149099999), W41 at 15 K: 2,774 hours a year; single years 2,489–2,909; lowest-year coverage 87%、15 K:每年 2,774 小时;单年 2,489–2,909;最低单年覆盖率 87%computed by this site本站计算2020–2024NOAA
Climate气候Visakhapatnam (Visakhapatnam Airport)维沙卡帕特南(维沙卡帕特南机场) (43149099999), W45 at 5 K: 8,754 hours a year; single years 8,739–8,760; lowest-year coverage 87%、5 K:每年 8,754 小时;单年 8,739–8,760;最低单年覆盖率 87%computed by this site本站计算2020–2024NOAA
Climate气候Visakhapatnam (Visakhapatnam Airport)维沙卡帕特南(维沙卡帕特南机场) (43149099999), W45 at 10 K: 8,617 hours a year; single years 8,492–8,697; lowest-year coverage 87%、10 K:每年 8,617 小时;单年 8,492–8,697;最低单年覆盖率 87%computed by this site本站计算2020–2024NOAA
Climate气候Visakhapatnam (Visakhapatnam Airport)维沙卡帕特南(维沙卡帕特南机场) (43149099999), W45 at 15 K: 6,611 hours a year; single years 6,352–6,856; lowest-year coverage 87%、15 K:每年 6,611 小时;单年 6,352–6,856;最低单年覆盖率 87%computed by this site本站计算2020–2024NOAA
Climate气候Delhi (Indira Gandhi Airport)德里(英迪拉·甘地机场) (42181099999), W17 at 5 K: 708 hours a year; single years 551–894; lowest-year coverage 96%、5 K:每年 708 小时;单年 551–894;最低单年覆盖率 96%computed by this site本站计算2020–2024NOAA
Climate气候Delhi (Indira Gandhi Airport)德里(英迪拉·甘地机场) (42181099999), W17 at 10 K: 59 hours a year; single years 24–76; lowest-year coverage 96%、10 K:每年 59 小时;单年 24–76;最低单年覆盖率 96%computed by this site本站计算2020–2024NOAA
Climate气候Delhi (Indira Gandhi Airport)德里(英迪拉·甘地机场) (42181099999), W17 at 15 K: 0 hours a year; single years 0–0; lowest-year coverage 96%、15 K:每年 0 小时;单年 0–0;最低单年覆盖率 96%computed by this site本站计算2020–2024NOAA
Climate气候Delhi (Indira Gandhi Airport)德里(英迪拉·甘地机场) (42181099999), W20 at 5 K: 1,353 hours a year; single years 1,127–1,544; lowest-year coverage 96%、5 K:每年 1,353 小时;单年 1,127–1,544;最低单年覆盖率 96%computed by this site本站计算2020–2024NOAA
Climate气候Delhi (Indira Gandhi Airport)德里(英迪拉·甘地机场) (42181099999), W20 at 10 K: 369 hours a year; single years 263–493; lowest-year coverage 96%、10 K:每年 369 小时;单年 263–493;最低单年覆盖率 96%computed by this site本站计算2020–2024NOAA
Climate气候Delhi (Indira Gandhi Airport)德里(英迪拉·甘地机场) (42181099999), W20 at 15 K: 5 hours a year; single years 0–14; lowest-year coverage 96%、15 K:每年 5 小时;单年 0–14;最低单年覆盖率 96%computed by this site本站计算2020–2024NOAA
Climate气候Delhi (Indira Gandhi Airport)德里(英迪拉·甘地机场) (42181099999), W25 at 5 K: 2,480 hours a year; single years 2,344–2,836; lowest-year coverage 96%、5 K:每年 2,480 小时;单年 2,344–2,836;最低单年覆盖率 96%computed by this site本站计算2020–2024NOAA
Climate气候Delhi (Indira Gandhi Airport)德里(英迪拉·甘地机场) (42181099999), W25 at 10 K: 1,353 hours a year; single years 1,127–1,544; lowest-year coverage 96%、10 K:每年 1,353 小时;单年 1,127–1,544;最低单年覆盖率 96%computed by this site本站计算2020–2024NOAA
Climate气候Delhi (Indira Gandhi Airport)德里(英迪拉·甘地机场) (42181099999), W25 at 15 K: 369 hours a year; single years 263–493; lowest-year coverage 96%、15 K:每年 369 小时;单年 263–493;最低单年覆盖率 96%computed by this site本站计算2020–2024NOAA
Climate气候Delhi (Indira Gandhi Airport)德里(英迪拉·甘地机场) (42181099999), W32 at 5 K: 4,625 hours a year; single years 4,365–4,869; lowest-year coverage 96%、5 K:每年 4,625 小时;单年 4,365–4,869;最低单年覆盖率 96%computed by this site本站计算2020–2024NOAA
Climate气候Delhi (Indira Gandhi Airport)德里(英迪拉·甘地机场) (42181099999), W32 at 10 K: 2,975 hours a year; single years 2,817–3,326; lowest-year coverage 96%、10 K:每年 2,975 小时;单年 2,817–3,326;最低单年覆盖率 96%computed by this site本站计算2020–2024NOAA
Climate气候Delhi (Indira Gandhi Airport)德里(英迪拉·甘地机场) (42181099999), W32 at 15 K: 1,799 hours a year; single years 1,576–2,073; lowest-year coverage 96%、15 K:每年 1,799 小时;单年 1,576–2,073;最低单年覆盖率 96%computed by this site本站计算2020–2024NOAA
Climate气候Delhi (Indira Gandhi Airport)德里(英迪拉·甘地机场) (42181099999), W40 at 5 K: 8,031 hours a year; single years 7,740–8,336; lowest-year coverage 96%、5 K:每年 8,031 小时;单年 7,740–8,336;最低单年覆盖率 96%computed by this site本站计算2020–2024NOAA
Climate气候Delhi (Indira Gandhi Airport)德里(英迪拉·甘地机场) (42181099999), W40 at 10 K: 6,221 hours a year; single years 5,915–6,575; lowest-year coverage 96%、10 K:每年 6,221 小时;单年 5,915–6,575;最低单年覆盖率 96%computed by this site本站计算2020–2024NOAA
Climate气候Delhi (Indira Gandhi Airport)德里(英迪拉·甘地机场) (42181099999), W40 at 15 K: 3,818 hours a year; single years 3,590–4,104; lowest-year coverage 96%、15 K:每年 3,818 小时;单年 3,590–4,104;最低单年覆盖率 96%computed by this site本站计算2020–2024NOAA
Climate气候Delhi (Indira Gandhi Airport)德里(英迪拉·甘地机场) (42181099999), W41 at 5 K: 8,219 hours a year; single years 7,947–8,483; lowest-year coverage 96%、5 K:每年 8,219 小时;单年 7,947–8,483;最低单年覆盖率 96%computed by this site本站计算2020–2024NOAA
Climate气候Delhi (Indira Gandhi Airport)德里(英迪拉·甘地机场) (42181099999), W41 at 10 K: 6,675 hours a year; single years 6,360–7,022; lowest-year coverage 96%、10 K:每年 6,675 小时;单年 6,360–7,022;最低单年覆盖率 96%computed by this site本站计算2020–2024NOAA
Climate气候Delhi (Indira Gandhi Airport)德里(英迪拉·甘地机场) (42181099999), W41 at 15 K: 4,186 hours a year; single years 3,945–4,466; lowest-year coverage 96%、15 K:每年 4,186 小时;单年 3,945–4,466;最低单年覆盖率 96%computed by this site本站计算2020–2024NOAA
Climate气候Delhi (Indira Gandhi Airport)德里(英迪拉·甘地机场) (42181099999), W45 at 5 K: 8,615 hours a year; single years 8,477–8,714; lowest-year coverage 96%、5 K:每年 8,615 小时;单年 8,477–8,714;最低单年覆盖率 96%computed by this site本站计算2020–2024NOAA
Climate气候Delhi (Indira Gandhi Airport)德里(英迪拉·甘地机场) (42181099999), W45 at 10 K: 8,031 hours a year; single years 7,740–8,336; lowest-year coverage 96%、10 K:每年 8,031 小时;单年 7,740–8,336;最低单年覆盖率 96%computed by this site本站计算2020–2024NOAA
Climate气候Delhi (Indira Gandhi Airport)德里(英迪拉·甘地机场) (42181099999), W45 at 15 K: 6,221 hours a year; single years 5,915–6,575; lowest-year coverage 96%、15 K:每年 6,221 小时;单年 5,915–6,575;最低单年覆盖率 96%computed by this site本站计算2020–2024NOAA